Ocotillo Pipelines (South Chandler Wastewater Force Main OWRF to AWRF and Water Transmission Main) 

Project Owner: City of Chandler
Project Type: Construction Manager at Risk
Construction Dates: 06/12 to 05/13

This CMAR project included the construction of more than six miles of new 42-inch diameter high-density polyethylene (HDPE) wastewater force main and five miles of new 24-inch diameter ductile iron pipe (DIP) water transmission main. Both pipelines extend along the Ocotillo Rd. (Dobson Rd. to McQueen Rd.) alignment in Chandler, AZ. The wastewater force main ties into the new lift station at Chandler’s Ocotillo Water Reclamation Facility near Queen Creek Rd. and Dobson Rd. and extends along Ocotillo Rd. to the Airport Water Reclamation Facility west of McQueen Rd. The water main ties into a water line near Intel at Dobson Rd. and Ocotillo Rd. and extends along Ocotillo Rd. to McQueen Rd. The project includes installation of manholes, valves, and six jack & bore crossings at utility-congested intersections as well as the Union Pacific Railroad crossing and Consolidated Canal crossing.

 




PROJECT AWARDS

ARIZONA PUBLIC WORKS
PROJECT OF THE YEAR 
American Public Works Association,
Arizona Chapter (AzAPWA)

BUILD ARIZONA AWARD
Associated General Contractors,
Arizona Chapter (AZAGC)

GRAND AWARD
American Council of Engineering Companies of Arizona (ACEC Arizona)

 

Facebook-Logo Achen-Gardner Construction Check out our Facebook page for more photos Northsight Boulevard Extension Project  CHECK OUT OUR FACEBOOK PAGE FOR MORE PHOTOS    09-28-12   10-25-12   11-27-12   01-30-13   03-01-13   03-29-13 

Achen-Gardner Construction Heavy Highway General Contractor Ocotillo Pipelines South Chandler Wastewater Force Main OWRF to AWRF and Water Transmission Main City of Chandler 42 inch diameter HDPE wastewater and 24 inch diameter DIP water main

3180101-Ocotillo-Pipelines-918px-30 Achen-Gardner Construction Heavy Highway General Contractor Ocotillo Pipelines South Chandler Wastewater Force Main OWRF to AWRF and Water Transmission Main City of Chandler 42 inch diameter HDPE wastewater and 24 inch diameter DIP water main


Achen-Gardner Construction Heavy Highway General Contractor Ocotillo Pipelines South Chandler Wastewater Force Main OWRF to AWRF and Water Transmission Main City of Chandler 42 inch diameter HDPE wastewater and 24 inch diameter DIP water main  3180101-Ocotillo-Pipelines-290px-380px-1 Achen-Gardner Construction Heavy Highway General Contractor Ocotillo Pipelines South Chandler Wastewater Force Main OWRF to AWRF and Water Transmission Main City of Chandler 42 inch diameter HDPE wastewater and 24 inch diameter DIP water main

Achen-Gardner Construction Heavy Highway General Contractor Ocotillo Pipelines South Chandler Wastewater Force Main OWRF to AWRF and Water Transmission Main City of Chandler 42 inch diameter HDPE wastewater and 24 inch diameter DIP water main

Achen-Gardner Construction Heavy Highway General Contractor Ocotillo Pipelines South Chandler Wastewater Force Main OWRF to AWRF and Water Transmission Main City of Chandler 42 inch diameter HDPE wastewater and 24 inch diameter DIP water main


Achen-Gardner Construction Heavy Highway General Contractor Ocotillo Pipelines South Chandler Wastewater Force Main OWRF to AWRF and Water Transmission Main City of Chandler 42 inch diameter HDPE wastewater and 24 inch diameter DIP water main




Achen-Gardner-Facebook4  LIKE US ON FACEBOOK              Achen-Gardner-Twitter4  FOLLOW US ON TWITTER            Achen-Gardner-YouTube4  WATCH US ON YOUTUBE