STREET TRANSPORTATION DEPARTMENT GENERAL CONSTRUCTION
Project Owner: City of Phoenix
Project Type: Job Order Contracting
Construction Dates: 07/17 to 07/20
This JOC includes a variety of civil construction including asphalt and concrete paving, concrete structures, removal and replacement of curb and gutter, wet utility improvements, storm drain and catch basins, etc.
Job Order #1: The Flower Street to Thomas Road project included 1,116 SY of asphalt pavement, 459 SF of sidewalk/driveways, 153 LF of curb and gutter, 2,205 LF of 18” storm drain, catch basins, and 20 sanitary sewer service relocations.
Job Order #2: The Montezuma Street and Carson Road project includes asphalt paving, sidewalk, curb & gutter, water meter boxes, and drainage grading.