Flood Irrigation Improvements: Parkway Boulevard, Mitchell Drive, and 15th Street

Project Owner: City of Tempe
Project Type: Design-Bid-Build
Construction Dates: 11/18 to 12/18

This project will improve irrigation services to Parkway Boulevard (College Avenue to Mill Avenue), Mitchell Drive (9th Street to 10th Street), and 15th Street (east of McAllister Avenue). Quantities include 1,098 LF of 15” ultraviolet light cured-in-place-pipe (UV CIPP), 383 LF 16” UV CIPP, 1,504 LF of 18” UV CIPP, 619 LF of 20” UV CIPP, 643 LF of 21” UV CIPP, 2 new manholes, reinstating of 49 lateral connections, and the removal of 69 LF of 12” pipe that will be replaced with 20” pipe.