North Tempe Waterline Replacement

Project Owner: City of Tempe
Project Type: Construction Manager at Risk
Construction Dates: 6/23 to 4/24

This project included approximately five miles of 8” and 12” waterline replacements throughout neighborhoods and along a high-volume arterial street. Also included were service connections, fire hydrants, other water appurtenances, sidewalks, curbs, gutters, driveways, pavement replacement, etc., as needed to complete the project.

The project included 4.6 miles of 8” and 12” waterline replacements as follows:

  1. Papago Manor Neighborhood/Concord Village included two miles of 8” waterline replacements.

  2. Rio East Neighborhood will included more than one mile of 8” and 12” of waterline replacements.

  3. Curry/Stadem/Miller Area included one half mile of 8” waterline replacements.

  4. Eaton University Industrial Park included 1,100 feet of 8” waterline replacement.

  5. Rolling Hills Golf Course included 1,200 feet of 8” waterline replacement.

  6. Maple Ash Neighborhood included less than one mile of 8” and 12” waterline replacement.