Verdin - CFD Infrastructure

Project Owner: Private Developer
Project Type: Construction Manager at Risk
Construction Dates: 05/24 to 03/26

This unique undertaking provided the on-site and off-site roadways and wet and dry utility infrastructure in support of the Verdin Housing Community built by Taylor Morrison. Delivered as part of a Community Facilities District (CFD), this infrastructure will ultimately be turned over to the City of Phoenix, requiring construction to City standards and in collaboration with City staff. Achen-Gardner brought our relationships with the City of Phoenix and City staff to ease this collaboration process.

Work consisted of 10 GMPs for on-site and off-site improvements:
Off-Site: These included improvements along Sonoran Desert Drive. Work included:

  • Roadway widening and extension of 17 box culverts and 10 pipe culverts to support the wider roadway section. In total, off-site work included 18,956 SY of pavement, 1,575 LF of curb and gutter, and 2,498 of concrete pedestrian ramps and median concrete paving.

  • Installation of 30,584 LF of 16” ductile Iron Pipe (DIP) water line along Sonoran Desert Drive from 7th Street to Cave Creek Road, and along Cave Creek Road from Sonoran Desert Drive to Jomax Road. Work also included 49 gate valves (8”, 12”, and 16”) and two new fire hydrants. We also installed more than 2,250 LF of 30” steel casing to protect this water line through the Apache Wash.

  • Installation of 32,717 LF of 12” dual HDPE force main along Sonoran Desert Drive from Verdin Way to Cave Creek Road, tying into the City of Phoenix’s existing system in the intersection.

  • Installation of 72 LF of storm drain 48”

  • Installation of 384 LF of storm drain 36”

  • Installation of 192 LF of storm drain 30”

  • Installation of 128 LF of storm drain 24”

  • Dry utilities coming from the east and west directions, working towards the new proposed community entrance from 7th Street and Cave Creek Road. These included new APS12kV power lines for APS, and joint trench for to include COX, Southwest Gas. 149,105 LF of conduit installed. 3,548 LF of sleeves of 5” and 1.25” sleeves.

  • New traffic signals and intersection improvements on Sonoran Desert Drive at 7th Street, Verdin Way, and Cave Creek Road.

On-Site: Work included:

  • Construction of Verdin Way, which was the main collector roadway for the community. In total, this included more than 35,407 SY of pavement, 31,043 LF of curb and gutter, and 5,904 SF of concrete pedestrian ramps, midblock ramps, and access ramps.

  • Installation of 7,290 LF of 12” DIP water line, including 15 – 12inch gate valves, 1,160 LF of 8” DIP water line and 11 – 8inch gate valves.

  • Installation of 18,200 LF of 12” dual HDPE force mains and 130 LF of 24” steel casing.

  • Installation of more than 7,600 LF of 24” to 36” storm drain and 138 LF 4 Barrel 10’x6’ box culvert, and a 124 LF 4-barrel 10’x6’ box culvert

  • Installation of new dry utilities, APS12kV power lines for APS, and joint trench for to include COX, Southwest Gas. 76,347 LF of conduit installed. 900 LF of sleeves of 5” and 1.25” sleeves. Construction of a 1 MGD (million gallons per day) lift station. The lift station included a polymer precast wet well, 2 pumps, Bioxide odor control system, mechanical components and plant piping, electrical equipment and instrumentation, SCADA, site security, masonry, asphalt paving, and concrete pavement.