Wet Utility Emergency Repair
Project Owner: City of Mesa
Project Type: Job Order Contracting
Construction Dates: 03/23 to 08/26
This job order contract covered emergency repair services for wet utilities throughout the City of Mesa. These emergency repair services included water, sewer, and irrigation lines throughout the City of Mesa. Repairs include:
Carbon unit installation at the Lehi Lift Station.
Assessment and removal of a 24” water valve and installation of five feet of 24" diameter water line.
Repair 8” CCP, removal of the old mortar coating, and restoration of the mortar lining.
Repair of a water main break at Gilbert Road and Southern Avenue. Our team received a call on a Friday and began work within an hour. We worked with the City of Mesa to perform work 24/7 across five days. This water main break hindered access to a bus station, which heightened the urgency to restore the road's usability.
Replacement of more than 40 feet of 42” HDPE sewer line at the intersection of Sossaman and Elliot Roads.